LawFinder.news
LawFinder.news

Bombay High Court Clears Path for Arbitration in Construction Dispute

LAW FINDER NEWS NETWORK | May 5, 2026 at 12:56 PM
Bombay High Court Clears Path for Arbitration in Construction Dispute

Court Appoints Sole Arbitrator to Address Contract Termination Conflict Between Generic Engineering and Maharashtra Maritime Board


In a significant ruling, the Bombay High Court has paved the way for arbitration in a dispute between Generic Engineering Construction and Projects Ltd. and the Maharashtra Maritime Board concerning the termination of a construction contract. The judgment, delivered by Justice Sandeep V. Marne, addresses the complex interplay of contractual clauses and their implications for arbitration.


The case revolves around a contract for the construction of an office building for the Maharashtra Maritime Board, which was terminated by the Board in August 2025. Following the termination, Generic Engineering sought resolution through arbitration as provided in the contract’s General Conditions, specifically Clause 25, which allows for arbitration of disputes. The Board, however, contested the applicability of arbitration for termination disputes, arguing that only decisions made by the 'engineer' were subject to arbitration, and that internal appeals should suffice.


The court examined the contractual framework, noting that Clause 25 of the General Conditions of Contract (GCC) explicitly provides for arbitration, despite conflicting clauses in the contractor's bid and the Special Conditions of Contract (SCC). Importantly, Clause 3.3 of the SCC, which initially excluded termination disputes from arbitration, was deliberately deleted, indicating the parties' intent to arbitrate such matters.


Justice Marne highlighted that the hierarchical departmental remedies outlined in the contract did not constitute a Dispute Review Expert, as required for arbitration. The lack of a mutual nomination for a Dispute Review Expert left Generic Engineering with no option but to pursue arbitration. The court dismissed the Board's argument that only decisions by the Executive Engineer, as 'engineer', were arbitrable, clarifying that the termination decision by the CEO was indeed subject to arbitration.


In conclusion, the Bombay High Court appointed Smt. Justice Anuja Prabhudesai as the sole arbitrator to resolve the disputes arising from the contract termination. The court's decision underscores the importance of honoring arbitration agreements and clarifies that conflicting contractual clauses should not nullify a clear intent to arbitrate.


The judgment marks a pivotal moment in promoting arbitration as a means to de-clog the overburdened courts and ensures that disputes, including those involving contract termination, can be resolved through arbitration.


Bottom line:-

Arbitration agreement exists between the parties for disputes arising out of contract/agreement, including termination of the contract, and an Arbitral Tribunal is constituted for adjudication.


Statutory provision(s): Arbitration and Conciliation Act, 1996 Sections 9, 11, 17


Generic Engineering Construction and Projects Ltd. v. Maharashtra Maritime Board, (Bombay) : Law Finder Doc id # 2889581

Share this article: