LawFinder.news
LawFinder.news

Bombay High Court Rules Settlement Agreement Supersedes Arbitration Clause in Original Contract

LAW FINDER NEWS NETWORK | December 18, 2025 at 4:03 PM
Bombay High Court Rules Settlement Agreement Supersedes Arbitration Clause in Original Contract

Court dismisses Mumbai Metro's bid to arbitrate under original contract, emphasizing the autonomy of the Settlement Agreement.


In a significant ruling, the Bombay High Court dismissed an application by Mumbai Metro One Private Limited seeking to refer a commercial dispute to arbitration based on an arbitration clause in their original contract. The dispute stemmed from a Settlement Agreement signed between Mumbai Metro One and Hindustan Construction Company, which did not contain an arbitration clause.


Justice Abhay Ahuja, presiding over the case, emphasized that the Settlement Agreement supersedes the original contract and its arbitration clause. The court held that the absence of an arbitration clause in the Settlement Agreement prevents disputes under it from being referred to arbitration, despite the original contract containing such a clause.


The case arose from a contract agreement dated August 16, 2010, between Mumbai Metro One and Hindustan Construction Company for the construction of the Mumbai Metro Line 1. This contract included a clause for arbitration in case of disputes. However, disputes led to the signing of a Settlement Agreement on March 28, 2024, which involved the return of performance bank guarantees and a payment of Rs.9 crore towards a full and final settlement.


Mumbai Metro One argued that the Settlement Agreement was executed in furtherance of the original contract and should thus be subject to the arbitration clause therein. They contended that the arbitration clause is autonomous and survives even after the original contract's termination. However, the court disagreed, stating that the Settlement Agreement intentionally departed from the dispute resolution mechanism of the original contract by including a governing law and jurisdiction clause that omitted arbitration.


The court noted that the Settlement Agreement explicitly superseded the original contract, as evidenced by Article 5 of the agreement which declared it a full and final settlement of obligations between the parties. The court further observed that the Settlement Agreement incorporated a clause specifying that it should be governed by Indian laws and that Mumbai courts would have exclusive jurisdiction, effectively excluding arbitration.


In delivering the judgment, Justice Ahuja referenced several precedents and statutory provisions, including Section 8 and Section 16 of the Arbitration and Conciliation Act, 1996. The court reiterated the principle that an arbitration clause does not survive when a subsequent agreement supersedes and novates the original contract without incorporating the arbitration clause.


The dismissal of the application means that Hindustan Construction Company can pursue its claim in court, seeking the payment of Rs.9 crore, along with interest, from Mumbai Metro One under the Settlement Agreement. The ruling underscores the importance of clearly defining dispute resolution mechanisms in agreements and the consequences of omitting arbitration provisions in settlement agreements.


Bottom Line:

Arbitration - Settlement Agreement supersedes the original contract - Absence of arbitration clause in Settlement Agreement prevents disputes from being referred to arbitration, even if original contract contained such a clause.


Statutory provision(s): Arbitration and Conciliation Act, 1996 Section 8, Arbitration and Conciliation Act, 1996 Section 16


Mumbai Metro One Private Limited, (Bombay) : Law Finder Doc Id # 2825431

Share this article: