LawFinder.news
LawFinder.news

Bombay High Court Upholds Arbitral Tribunal's Award in Siemens vs. Paharpur Cooling Towers Dispute

LAW FINDER NEWS NETWORK | June 12, 2026 at 5:13 PM
Bombay High Court Upholds Arbitral Tribunal's Award in Siemens vs. Paharpur Cooling Towers Dispute

Court Dismisses Paharpur's Petition Challenging Findings on Risk Purchases, Liquidated Damages, and Bank Guarantee Invocation


In a significant ruling, the Bombay High Court has dismissed the petition filed by Paharpur Cooling Towers Ltd challenging the arbitral award granted in favor of Siemens Limited. The petition, filed under Section 34 of the Arbitration and Conciliation Act, 1996, was rejected by Justice Somasekhar Sundaresan, who upheld the arbitral tribunal's findings regarding risk purchase claims, delay and liquidated damages, and the invocation of bank guarantees.


The dispute arose from contracts executed between Paharpur and Siemens for the construction of cooling towers at Torrent Energy Ltd.'s power project in Dahej, Gujarat. The arbitral tribunal had earlier awarded Siemens Rs. 53.53 crores, with Paharpur's counterclaims being partly allowed, resulting in a net payable amount of Rs. 20.84 crores by Siemens to Paharpur.


Paharpur's petition specifically challenged the tribunal's findings on three issues: the allocation of risk purchase claims, the delay and imposition of liquidated damages, and the invocation of bank guarantees. The High Court meticulously analyzed each of these contentions.


On the issue of risk purchase claims, Paharpur argued that the arbitral tribunal's grant of 50% of the disputed claims was arbitrary and lacked evidentiary support. However, the High Court held that the tribunal's approach was reasonable and fell within its discretion, emphasizing that re-appreciation of evidence is not permissible unless there is patent illegality or irrationality.


Regarding delay and liquidated damages, Paharpur contended that the tribunal failed to properly apportion the delay between the parties, which led to an unjust award of maximum liquidated damages to Siemens. The High Court found that the tribunal's findings were based on a thorough examination of evidence, including contemporaneous meeting minutes and correspondence, and thus did not warrant interference.


Lastly, on the matter of bank guarantees, Paharpur challenged the tribunal's dismissal of its counterclaim as an "academic issue." The High Court upheld the tribunal's reasoning, which treated advance payment guarantees as performance guarantees, and found no mala fide intent in Siemens' invocation of the guarantees.


Justice Sundaresan reiterated the limited scope of interference under Section 34, stressing that arbitral awards should only be set aside for patent illegality, irrationality, or lack of reasoning. The court concluded that none of these grounds were established by Paharpur, leading to the dismissal of the petition.


This judgment reinforces the principle that courts should not lightly disturb arbitral awards unless substantial grounds for intervention are demonstrated, thereby affirming the autonomy of arbitral tribunals in commercial disputes.


Bottom line:-

Arbitration and Conciliation Act, 1996 - Challenge under Section 34 to arbitral award - Court upheld the arbitral tribunal's reasoning and findings on risk purchase claims, delay and liquidated damages, and invocation of bank guarantees, emphasizing that interference is limited to cases of patent illegality and irrational findings.


Statutory provision(s): Arbitration and Conciliation Act, 1996 Section 34


Paharpur Cooling Towers Ltd v. Siemens Limited, (Bombay) : Law Finder Doc id # 2918371

Share this article: